Pate Garver’s Three Decades in Trenchless Technology Magazine
Pate Garver carries forward the microtunneling legacy of BRH-Garver, whose roots date to the mid-1970s and whose first microtunnel project began in Houston, Texas, in 1986. That project, River Oaks, is recognized as the first U.S. microtunneling project using pipe diameters too small for personnel entry. Nine years later, Trenchless Technology named Mike Garver its 1995 Person of the Year, observing that any discussion of microtunneling in North America ultimately turned to BRH-Garver and Mike Garver. That early recognition established a theme reflected in the magazine’s coverage of our work ever since: a sustained role in advancing microtunneling in North America.
That coverage has stayed consistent over the years. Trenchless Technology’s annual North American Microtunneling Job Log has tracked our work in the field year over year, and the 2024 edition alone documented five separate Pate Garver installations across Houston, each tied to the City’s consent decree with the EPA.
The Chelford City projects covered the third and fourth phases of the diversion program, following phases 1 and 1A, and finished in 2025 on the west side of town. Microtunneling eliminated lift stations along more than 11,000 linear feet of Hobas Pipe, with a little Logan Clay pipe and Permalok casing thrown in.

The Easthaven Wastewater Treatment Plant flow diversion on the southeast side is still active. It involves a 60-inch pipe over more than 6,000 feet, with non-driven, water-tight shafts placed near existing homes.
The JFK Lift Station rehabilitation, on the northeast side of town near George Bush Intercontinental Airport, eliminated a station and finished in 2024, in under four months.
None of these projects made headlines on their own. Together, in the pages of the industry’s own record of the year’s work, they show a contractor doing the unglamorous, technically demanding work that keeps cities running.
Trenchless Technology also recognized David Ellett with its 2026 Microtunneling Achievement Award, an honor tied to the same short course and community that first put Mike Garver’s name in print thirty years ago. The through line is the company. The same commitment to trenchless methods that earned attention in 1995 still shows up in project logs three decades later.
Recognition from the trade press is always welcome, but we pay closer attention to what the job log shows. A record built one installation at a time reflects how agency engineers and inspectors saw the work, and it is the same record we bring to every new project. For public works staff and design engineers weighing microtunneling or other trenchless methods, we are glad to talk through what has worked on similar alignments. You can reach us at pategarver.com.